the wood floor planks are delivered
the tubing being laid for the snow melt
the retaining wall for the patio
the stamped concrete for the patio is poured on the west side of the patio
the east side of the patio leveled and readied for concrete. it is supposed to snow tomorrow. hopefully concrete will be poured on friday.
another look at the stamped concrete
the sheet rock is in, now the taping is going on
the opening from the main floor to the basement
the basement kitchen area walled off
work is going on with the trex decking being installed and a flagstone landing for the steps from the deck down to the patio
the steps from the driveway to the flagstone landing
when the inspection took place, we were told that the previous window well did not meet code. the window well was dug out and enlarged. a new window well was installed with a ladder and metal cover.
the outside of the house was painted. the siding was painted with a cream color and the trim was a beige color. the accent color is blue on the shutters and doors.
door from the laundry room to the deck
the trex decking is being installed.